London Array Offshore Wind Farm - Array Cable Installation

 

The London Array wind farm is located approximately 20 km (12 miles) from the Kent and Essex coasts in the outer Thames Estuary. The wind farm consists of 175 turbines with a capacity of 630MW. The site is situated on and between two sandbanks, Long Sand and Kentish Knock, in water of up to 23 metres deep. It is bounded to the west by Black Deep, the main approach to the Port of London, and to the south by the approaches to Fisherman's Gat.

 

Facts and figures

Infield Cables
xx nos
Vessel
Normand Flower, Stemat Oslo, Pontra Maris
Project categories

London Array world's largest wind farm

The turbines are mounted on monopole foundations and connected by marine cabling at 33 kV to two offshore substation installations where the voltage is stepped up to 150 kV for export to shore. The power generated is exported via four 150 kV cables (two per offshore substation) to a landfall point at Cleve Hill, Graveney, England. Once the marine cables reach the shore they pass under a sea defence and borrow pit using HDD conduits. The export cables cross the Kentish Flat and Britned cables.

 

How it all began

The idea for the London Array project was conceived in 2001, when a series of environmental studies in the outer Thames Estuary confirmed the area was suitable as a wind farm site. Two years later, the Crown Estate gave London Array Ltd a 50-year lease for the site and cable route to shore.

Planning consent for a 1GW offshore wind farm was granted in 2006, and permission was granted for the onshore works in 2007. Work on Phase One started in July 2009 with the building of the onshore substation at Cleve Hill in Kent.

 

  • Phase One, Facts and Figures:
  • Phase One, Facts and Figures:
  • An offshore area of 100km2
  • 175 wind turbines
  • Two offshore substations
  • Nearly 450km of offshore cabling
  • One onshore substation
  • 630 MW of electricity
  • Enough power to supply over 470,000 homes a year – two-thirds of homes in Kent
  • CO2 savings of 925,000 tonnes a year

 

Completion of the construction on Phase One took place at the end of 2012

Project location

View project on map »

Related items:

News Alerts

A Boskalis Company
xThis website is optimized for Internet Explorer 7.0 or higher and Firefox 3.5 and higher. Unfortunately, if you use of a lower browser version it will have consequences for the optimal viewing of this website.